Good Morning Everyone,
Well what can I say, this crazy weather hasn't stopped the team from "cracking on" with this job.
The valve chamber pipework is all installed and the concrete work is now complete on the main building. The security covers are being fitted to the de-chlorination chambers, and some major components too....ie thrust blocks and pipe supports. The security doors to the treatment building have been fit and internal work has now started with the building with the plaster boarding to the kitchen along with the first fix of plumbing.
The weather certainly has been challenging to say the least and the team have certainly risen to that challenge.
Once again here are some photos.