Update by Joan Tatters
Good Morning,
Hope you all enjoyed the lovely Spring like weather at the weekend...............but kept safe!
This weeks update from the team:-
Treatment building - Our subcontractor continued installing the cabling within the building, we installed the last door on the west side of the building, cabling and analyser boards were fixed and as you can see by the photos the cladding was erected to make the building watertight.
Contact Tank - All stoned up, shuttered and installed mesh then poured the concrete base for the stairs.
Water Settlement Tank - The shutters and concreted plinth for decant arm was installed in the east tank as well as more pipework.
Thank you all again for your patience.