Update by Gabrielle Ward
Good afternoon!
Since our last update in April, the team have been progressing with installing the new pipeline! In total, 484m of pipeline has been installed.
We are currently carrying out the construction of the pipeline in the Rockwill development. So far, just in this area alone 596m of pipe has been welded together in preparation for the drilling works to commence when we return from the Bank Holiday.
Paul and I had the priviledge of meeting some of you at the start of the month when we came to discuss our working area set up in the grassed area of Lartington Way.
You will start to notice the team setting up the working area from next week where we will be erecting the new heras fencing, laying stone and setting up the mobile all in one unit ready for the drilling works to commence in the next month or so. I have included the working area set up for Lartington Way here.
As always, if you have any questions please feel free to leave a comment below and a member of the project team will get back to you.
Have a lovely weekend!
Gaby