Good morning,
It has been a busy month on site and work has been progressing well since our last update.
The team have now installed the full length of the pipe which is 1645m of pipeline. The drilling work underneath the A67 that was mentioned in our last update was completed successfully. I have included some photos and a video of the directional drilling below. The final connections are yet to be carried out at Allens West Station and the Rugby Pitch on Aislaby Road.
We are pleased to let you know that we have completed our work within the Rockwill development, and the reinstatements have been carried out.
Currently, the team are building air valve 1 in the compound field, and air valve 4 at Lartington Way.
After liaising with the rugby club, we have offered and agreed to extend their car park which will reduce the number of parked cars along Aislaby Road.
We will also be reinstating the running track in Egglescliffe school field which will be finished mid-October.
I've included some photos for you to look over. If you have any questions, please leave a comment below and a member of the team will get back to you.