GENERAL PROJECT

Aislaby Road Rising Main

Project to replace a failing pumping main from Aislaby Road Pumping Station to Allens West, Eaglescliffe.

Update by Gabrielle Ward

Good afternoon,

Just a quick update on whats been happening on site over the past month. Although the recent storms have been working against us, we are continuing to progress well. 

The team are currently in the process of demobilising our site compound at Lartington Way ready for reinstatements and top soiling to commence. During this time, you may notice an increase in vehicles taking material from this area. We have arranged a road sweep to maintain this area to ensure the roads are kept clean and tidy. 

We are aiming for the final connections in the rugby field and at Allens West to be complete within the next two weeks. 

I will be posting another update in the upcoming weeks, so keep a look out.

Thank you for your continued patience.

Gaby

Please Login in order to comment on this update.

View all updates
Work in your Community

Work in a business that supports your community

At Northumbrian Water, we work to make a difference in your community.

Have you considered a career that can help you do the same?

As well as the teams you see working in your streets, we have people doing a wide range of jobs that support that work to deliver the best possible water and sewerage services across the North East.

You can find out more about careers with Northumbrian Water and check out the latest vacancies by following the link below.

www.nwl.co.uk/careers