Hi all,
Following my update in May, we can now confirm that reinstatement work has begun.
This morning, we started on the Yarm School fields, focusing on muck away and extending the car park. We aim to complete full reinstatement of this section by next Friday, the 21st of June.
Work on Lartington Way will start towards the end of this week, and we hope to have this completed by next Friday, the 21st of June as well.
Egglescliffe School's running track is expected to be finished next week, with the reinstatement to be completed the following week. Overall, we are aiming to have all sections completed by Friday, the 28th of June, weather permitting.
If you have any questions, please comment below and one of the team will get back to you. We would like to thank you for your patience while our work is ongoing to restore your area to its former beauty.