Deepdale Water Main Renewal, Barnard Castle

We will be investing £900,000 in our strategic trunk mains network. This work will help secure and maintain water supplies into the future, this work will not affect your water supplies.

Project updates

Update by David Player

Good Afternoon,
Due to the weather over the last few days increasing hazards on site and the difficulties getting to site we have not been working. Today we intend to ensure the site is safe to restart works on Monday.
We apologise for any inconvenience, we will do our best to catch the time up.  Have a good weekend.
Thank you
David

Please Login in order to comment on this update.

Update by John Cartwright

Afternoon all, i was going to say good afternoon, but looking at the weather forecast for the next couple of days we may be in for some rough weather?

Can i ask everyone to please take care when driving down or up Lartington Lane over the next week or so. As you may be aware we have started work on the East side of the river, however due to some unforeseen circumstances we have stopped work temporarily, but we will be re-starting work in this area tomorrow. There are still places for people to park & walk the dogs or just have a nice walk along the river, just be aware that the Aquaduct is now closed until we complete our works.

Thanks, john.

Please Login in order to comment on this update.

Update by John Cartwright

Morning,

Just a quick update about the closure of the Aquaduct, we have decided to put the footbridge closure back to Monday 19.02.18

We are also constructing a temporary footpath running through the working area as we will be closing the footpath on Lartington Lane while we carry out the pipe installation through the road & footpath it's self.

Again we apologies of any inconvenience and ask for everyone to be patient.

 

Thanks, john.

Please Login in order to comment on this update.

Update by John Cartwright

Afternoon,

As you may be already aware we are in the process of changing the traffic management on Lartington Lane to allow us to continue with the works on the opposite side of the road.

We will also need to close the footpath to allow us to carry out this work, but we will be installing a temporary footpath from the entrance to the Aquaduct to the bollard protected entrance further along the road.

we will also be closing the Aquaduct footbridge by the end of the week, and there will be a diversion in place and it will be sign posted.

I would like to take this opportunity to thank everyone for their patience and understanding during the works.

 

Thanks, john.

Please Login in order to comment on this update.

Update by John Cartwright

Good afternoon to all using the portal for information.

Hopefully within the next week, we should be completing works on the east bound side of Lartington Lane, and be moving the traffic management to the West bound carriageway to allow us to continue the works. As these works include the installation of the overland rider, we will be looking to close the Aquaduct footbridge week commencing 12th February 2018. It may not be on the Monday that we close the Aquaduct, but the diversion route will be in place & sign posted.

I will apologies in advance for any inconvenience caused by the closure of the Aquaduct, but it is necessary to enable us to complete the works and keep everyone safe.

 

Thanks, john.

Please Login in order to comment on this update.

Update by John Cartwright

Afternoon Everyone,

As you can see we have returned to work this week to continue with the water main upgrade. I apologies for any inconvenience during the installation of the Traffic Lights, but it all appears to be running well now.

As my collegue has already stated the Aquaduct will remain open for a few more weeks, we will let everyone know closer to the time as to when the Aquaduct will be closed to allow us to carry on with the works.

 

Thanks, John.

Please Login in order to comment on this update.

Update by Christine Taylor

Happy New Year,

As you may of noticed our team have returned to site.  We will be posting an update very soon.

In the meantime please be advised that the Deepdale Aquaduct will remain open until the end of the month.  We will advise closer to the time when we intend to close the bridge for a period of time.

Thank you for your continued understanding whilst we carry out our works.

Christine

Please Login in order to comment on this update.

Update by Christine Taylor

Good morning,

A quick update before we finish for Christmas.  All our traffic management will be removed for the festive period from 22 December 2017 to the 8 January 2018.

The Deepdale Aquaduct will not be closed from the 8 January 2018, it will be later in the month.  We will notify both residents and the local community of an accurate date in January 2018.

We want to wish you all a Merry Christmas and all the very best for 2018, and all our staff hope you enjoyed our Christmas video last week.

If there are any issues over the festive period please contact 03457 171100, this is a 24 hour numbers.  During working hours (except weekends and bankholidays) I will be available to assist with any queries.

See you all in 2018

Christine

 

Please Login in order to comment on this update.

Update by John Cartwright

Good afternoon to everyone,

I hope the weather hasn't caused anyone too many problems when driving. the constantly changing can make traveling difficult and sometimes hazardous, so can i please ask that everyone takes extra care over the coming holiday period.

We are over the next few days completing some works in the road & the verge on Lartington lane. we will be removing fencing form the road and opening the road back to normal operation for the holiday period. So everyone is aware we will be removing the Traffic Management on Thursday afternoon 21.12.17. Upon our return to work following the holidays we will be putting the TM back in place on Tuesday 9th January 2018.

Form all on site i would like to thank everyone for there patience and understanding while we carry out the works.

I hope you all have a Happy Christmas.

Thanks, john. 

Please Login in order to comment on this update.

Update by John Cartwright

Afternoon,

It may not look as if we are progressing a great deal with the works on Lartlington Lane, However we are progressing well with the new pipe work in the verge area, and will be continuing with the works into the carriageway within the two-way lights. Too keep everyone up to date we will be removing the two-way lights on Thursday 21st December 2017 for the Christmas holidays. The lights will be put back in place on Tuesday 9th January 2018 to allow us to complete the works in the carriageway.

We have started the excavation works within the field adjacent to Lartington Lane opposite the works in the verge.

Following the resent change in the weather (getting colder) i would ask that everyone take extra care when approaching the road works.

I would again ask for your patient and understanding during this time.

 

Thanks, john.

 

Please Login in order to comment on this update.

Work in your Community

Work in a business that supports your community

At Northumbrian Water, we work to make a difference in your community.

Have you considered a career that can help you do the same?

As well as the teams you see working in your streets, we have people doing a wide range of jobs that support that work to deliver the best possible water and sewerage services across the North East.

You can find out more about careers with Northumbrian Water and check out the latest vacancies by following the link below.

www.nwl.co.uk/careers