Update by Gabrielle Ward
Hello,
I hope everyone has had a lovely weekend.
Here is a quick update on our work and what to expect in the upcoming weeks.
Work is progressing well on site, and I am pleased to let you know that we will be re-opening Mayfair Road junction later on today. Work will continue at the bus terminus adjacent to North Road and Longfield Road until the end of August.
The next stage of work will take place along Lemon Grove for around two weeks, and the junction of Myrtle Gardens for upto four weeks. It is necessary to implement a road closure on the junction of Myrtle Gardens and a two-way traffic light system along Mayfair Road during this time.
Access to Myrtle Gardens will be maintained via Glebe Road.
I would like to reassure you that we will do all we can to keep disruption to an absolute minimum, and all residential and emergency access will be maintained at all times. However, should you require any assistance our site team will be happy to help.
Please feel free to leave a comment below with any questions you may have.
Thank you for your continued patience during this time.
Gaby