The construction phase of this project is now complete.

There may still be updates, so the project will remain here. We are still monitoring the project and will reply to any comments. So if you have any questions please feel free to comment or contact us here.

GENERAL PROJECT

Heads Hope Dene, Co. Durham

This project is to reduce the risk of pollution to Head Hope Dene. A range of solutions are being investigated to reduce the risk of pollution caused by flooding from the sewer due to blockages, and land slip. Construction is programmed for 2021/22.

Update by Gabrielle Ward

Good Afternoon,

It's been a couple of weeks since we started setting up site for our work. 

If you have had a walk along the footpath located near the site compound, you will have noticed some changes! The track leading to the compound from Front Street has been re-graded and the pot holes have been filled. 

The stone has been laid for the compound area, and the site cabins are now set up.

We have started the enabling works on the SPS (Sewerage Pumping Station) compound area including the new access track. 

I will be posting regular updates on how work is progressing on site, so keep a look out!

If you have any questions, please feel free to leave a comment on this post or visit the "contact" button at the top of the page.

We are more than happy to help!

Thanks,

Gaby

 

 

 

Please Login in order to comment on this update.

View all updates
Work in your Community

Work in a business that supports your community

At Northumbrian Water, we work to make a difference in your community.

Have you considered a career that can help you do the same?

As well as the teams you see working in your streets, we have people doing a wide range of jobs that support that work to deliver the best possible water and sewerage services across the North East.

You can find out more about careers with Northumbrian Water and check out the latest vacancies by following the link below.

www.nwl.co.uk/careers