Update by Gabrielle Ward
Good afternoon,
It's been a couple of weeks since my last update, here is how our work is progressing on site:
Sewage Pumping Station - landscaping around the SPS is now 90% complete. The site team are currently installing security covers to the shaft and security fencing around the SPS area.
Upstream gravity - Our subcontractors, Active Tunelling, have been busy working on the upstream gravity pipeline. Manholes 1 & 2 are now complete and the pipeline from manholes 3 & 4 are currently under construction. This will then tie in to the existing network.
Downstream gravity sewer - directional drilling works complete between manhole 11 and 16. The team are currently constructing the manhole chambers 11, 13, 14 & 15.
I have included a map which shows the different locations of our working areas, along with some photos.
As always, thank you for your continued patience and support.
Speak soon.
Gaby
Please Login in order to comment on this update.