GENERAL PROJECT
CURRENT WEATHER
9°C

Horsley Water Treatment Works Upgrade

A £46M project to upgrade Horsley WTW has now reached a key milestone. We have selected our partner Mott MacDonald Bentley (MMB), to upgrade the treatment works.

Project updates

Update by Shafqat Akbar

In today's update I want to show you how much work is happening on this site. Here are some of the many work fronts that are currently open.

This is the first concrete pour for the passavant crane base.

The lamella structure in the sludge area has been positioned into it's permanent location. The fit out has started.

The scaffold enclosure to the HV swithroom is in place. Works inside this structure is ready to start.

The silos are ready to receive the first deliveries of chemicals.

 

Please Login in order to comment on this update.

Update by Shafqat Akbar

Hello everyone. At Horsley, we have achieved another milestone. We have completed the deep pipelines, reinstated the fencelines and the automated barriers in the Middle Road area of the site. We are ready to re-open Middle Road. 

The project team is working on a number of fronts and continue to make good progress. 

We have started the testing and commissioning of the MEICA works.

The fit out of buildings continues. We have a number of specialist partners on site working on this project.

 

Please Login in order to comment on this update.

Update by Shafqat Akbar

Hello from Horsley. We have been working on many new fronts at Horsley and we are hitting a lot of milestones. Thank you to the site teams on the hard work and dedication. We have tested and commissioned many areas of the water treatment process. We have connected permanant power to many of the new strucures and MCCs. 

The site team has set up a the temperature monitor at the entrance to the main office block. This temperature monitor compliments all of the other covid-19 management the site has set in place.

Please Login in order to comment on this update.

Update by Shafqat Akbar

We have had another week of good progress at Horsley Water Treatment Works. Here are some photos showing how the project is going.

This is the view from the top of Birney Hill pumping station looking west along the Tyne valley

The underground works in Middle Road are progressing well. The deep pipes are complete in this area.

We are progressing well with the installation of external access and fittings.

Please Login in order to comment on this update.

Update by Shafqat Akbar

Today I would like to update you on the good progress that has been made at Birney Hill pumping station.

Most of the pumping station is hidden from view. These two structures are built on top of the pumping station.

The earthworks operations are progressing well.

Some of the equipment is housed behind block walls and steel fencing

Please Login in order to comment on this update.

Update by Shafqat Akbar

Hello. We achieved another one of our project milestones this week. We lifted the surge vessels into their final positions.

This crane lift was carried out in two phases. We lifted the vessels onto trailers and transported them to the second lifting location.

We lifted the 14 tonne vessels over a building and onto the reinforced concrete reception slab

The two vessels have been secured into their final positions. The mechanical and electrical fit-out will start later this week

 

Please Login in order to comment on this update.

Update by Shafqat Akbar

Progress on this project has been excellent over the summer months. Many of the new structures are nearing completion. Here are some of the new structures that have been built.

These silo have been installed and the delivery pipes are being completed

The fit out of the buildings is progressing well. We have installed some of the emergency showers.

The installation of the process plant and construction of the delivery slabs are progressing well 

Please Login in order to comment on this update.

Update by Shafqat Akbar

We are ready to start buiding the fuel delivery slab next to one of the existing buildings at Horlsey. The reinforcement is on site.

Please Login in order to comment on this update.

Update by Shafqat Akbar

Hello. This is a quick update about how much work has been done at Horsley. We are progressing well.

Please Login in order to comment on this update.

Update by Amanda Hunt

Good Afternoon Horsley

Please accept my apologies for the lack of updates, I am sure you will all understand that the Covid 19 lockdown has thrown us all.

Today we have delivered an update letter to the residents of Horsley regarding some work we are planning to carry out this week. The information in the letter is outlined below.  

We have fewer colleagues available to speak with you due to coronavirus and it may take longer to answer your call on 0345 717 1100 so if you would like more information you can contact the project team by using the contact us button above or by commenting on my post.

Stay safe.

Amanda 

----------------------------------------------------------------------

Dear Customer

Work at Horsley Water Treatment Works

As part of our on-going investment to upgrade the works and to secure water supplies into the future, I’m writing to let you know about some additional work this week which may generate some noise from our site.

From 9am on Tuesday 23 June 2020, to 5pm on Thursday 25 June 2020, we will be continually running some additional pumps within the site boundary and this may generate some low level background noise throughout the duration of the work. Please accept my apologies for the short notice in letting you know about this essential work.

We will do everything we can to keep disruption to a minimum and I would like to thank you for your patience as we continue to work within your community. There will be no disruption to your water supply.

If you have any queries about this work, please telephone our customer contact centre on 03457 171100 or tweet us @nwater_care. You can also find out more information as work progresses at www.nwlcommunityportal.co.uk and follow the link to the Horsley page.

Yours sincerely

Mike Forster 

Project Manager

 

 

Please Login in order to comment on this update.

Work in your Community

Work in a business that supports your community

At Northumbrian Water, we work to make a difference in your community.

Have you considered a career that can help you do the same?

As well as the teams you see working in your streets, we have people doing a wide range of jobs that support that work to deliver the best possible water and sewerage services across the North East.

You can find out more about careers with Northumbrian Water and check out the latest vacancies by following the link below.

www.nwl.co.uk/careers