Update by Geoff Joyce
Hi, everyone,
please find below an udate on progress at Horsley WTW to Friday, 22 July, 2016.
Works have continued to the excavation for the Actiflo and Rapid Gravity Filters area at the north-west corner of the site. The excavated material generated is being stockpiled at the southern boundary of the site and will be maintained for use in backfilling operations later in the project. An existing mound to the east of our excavation has this week been removed to facilitate future works in this area. This was made possible by the diversion works to an existing pumped main ( which I reported on in the previous update).
Works to facilitate removal of existing overhead power lines serving the WTW continued throughout the week. Replacement underground cables have been laid along the western verge of Water Lane. These will be connected and energised by Northern Power Grid in the near future. (This work was originally planned for weekend of Saturday 23 and Sunday 24 July, but a threat of forked lightning for the area has slightly delayed operations).
Site staff are now comfortably settled in the site compound area accommodation.
I have attched some progress photos to the update.
Have a nice weekend.
Geoff
Please Login in order to comment on this update.