Update by Geoff Joyce
Hi, everyone
Here's the latest update for Horsley WTW Upgrade:
As reported last week we have continued with steelfixing and formwork erection to the walls in the Actiflo area at the north end of the working area. We intend to place concrete to these walls on Friday ( 21 October, 2016 ). The quantity of concrete in these wall pours is much smaller than the quantities required for the base slab pours which we completed earlier. The time taken to place the concrete is, however, restricted by the height to which it can be placed per hour. This is necessary to control the pressure on the formwork as the concrete is placed. We will complete the initial wall pour during the working shift on Friday. We may, however, need to work to a slightly later time to complete the finishing works to the top surfaces of the walls. This work requires only a couple of concrete finishers to trowel off the exposed top surface of the walls. The timing depends on the curing (setting) of the concrete which will be influenced by weather conditions at the time. Should we need to work later than the nomal hours the work will produce minimal noise. I have appended some photos of the formwork erection in progress.
We also commenced work this week to install rock anchors to the Rapid Gravity Filters area to the south of the Actiflo. Believe it or not, but the large concrete tanks we are constructing below ground level can, given the right (or wrong) groundwater levels, float. We can calculate the upthrust that we need to guard against flotation thanks to my old schoolmate Archimedes (he was a right swot at school was Archie). The anchors are installed by drilling to a calculated depth in the rock below our excavation and grouting in heavy steel rods. The tops of these will then be cast into the base slab when we place concrete to the slab. In total there are 109 anchors to be installed. We are installing 6 of these this week, and will carry out testing, the results of which will be available next week. Successful test results will then allow us to install the remainder of the anchors (planned to take another 2 weeks after that). I have posted a photo of the drill rig in operation.
We will update regularly as work progresses.
Regards
Geoff
Please Login in order to comment on this update.