Update by Geoff Joyce
Hi everyone,
the weeks are flying over!
Please find below update for the works to Friday, 5 August 2016:
Excavation continued to the Actiflo and Rapid gravity filters areas in the NW corner of the site (photos attached). Excavated material was stockpiled on the spoil heap at the SE corner. This heap is now completed and topsoil was spread to the heap during the latter part of the week (see photo).
A new haul route was developed to allow further excavated material to be stockpiled in the SW corner of the site (see photo).
Northern Power grid returned to site to continue work to the diversion of overhead high voltage cables to a new underground route. New poles have been erected to replace redundant ones which will be removed when diversion works are complete (see photo). The work will continue over the weekend of Saturday, 6 and Sunday,7 August, 2016.
Enjoy the weekend. Watch out for the winds on Sunday.
Geoff
Please Login in order to comment on this update.