The rotavating and seeding within the North field and Birtley Sewerage Treatment Works is on hold and will be carried out in the Spring.
Auger bore and directional drilling works are complete with the concrete reinstatement inside Birtley Sewerage treatment works ongoing.
The design for Lamesley pump station has been approved for the installation of the new pipework to the existing chamber and the new wash out chamber, works started Monday 16 October 2023 for approximately 4-6 weeks.