Update by Steve Boyd (Project Manager)
Hi everyone
Here is this weeks progress for the scheme:-
Marden Road South
Underground tunnel boring operations:- Following a slight delay due to ground conditions last week, we have recommenced drive 2 this week and progress has been very good so far, to date we have tunneled approximately 22.3 meters across Marden Road South just onto Burnside Road which will continue next week.
Along with the above operation, we have excavated the reception pit in preparation to receive the Underground tunnel boring. machine.
Underground tunneling works Drive 1 into the existing chamber within the Scouts Hut area is now complete, reinstatement works are continued along with turning the flows once all underground tunneling works are complete.
Burnside Road
Open Cut Drainage Works:- We have progressed really well this week working our way up to the junction of Hatherton Avenue with permanent tarmac operations following behind to open up the highway as soon as practically possible for residents access on their drives, however there will be further localized works to be carried out for the permanent reinstatement of the speed ramps at a later date, works will continue next week.
Apologies to those residents still affected by our works although we are endeavoring to progress as quickly as possible to complete the new drainage network.
Have a nice weekend.
Steve.
Please Login in order to comment on this update.