Update by Paul Davison
Good morning, it’s been a little while since the last update and I thought I better bring you up to date with progress on site.
The vast majority of the pipework within the St George’s site is now complete and we are finishing off the final connections including pressure testing the last section of the rising main. We have made a start reinstating the link road between St George’s Hospital’s car parks and sections along Cottingwood Lane and expect to be complete and demobilised by Friday 9 June.
Meanwhile, Linden Homes’ contractor, Esh Construction are continuing with drainage work on St George’s bank with foul drainage complete up to the site entrance. Work will be continuing for the foreseeable future as they progress past the site entrance towards St George’s Hospital with the foul drainage. Once complete, they will be continuing with further road and drainage improvements and expect to be complete later this summer.