Update by Anya Lowes
Hi all,
We wanted to let you know we will be working this weekend on site, on the 22nd & 23rd of March.
If you have an issues or queries please contact Jason our site agent on 07970248988.
Thanks.
This project is to provide environmentally friendly fish exclusion screens at the raw water pumping station at Ovingham. These screens are necessary to protect the European Eel and other fish species that are present in the River Tyne. Work will commence April 2023 and anticipated to be complete March 2025
Hi all,
We wanted to let you know we will be working this weekend on site, on the 22nd & 23rd of March.
If you have an issues or queries please contact Jason our site agent on 07970248988.
Thanks.
Hi all,
We wanted to let you know we will be working this weekend on site, on the 15th of March.
If you have an issues or queries please contact Jason our site agent on 07970248988.
Thanks.
Please Login in order to comment on this update.
Good afternoon, Everyone,
I bet you are all pleased we are entering the lighter nights and hopefully some better and improved weather!!
Its been a while so I thought I would let you know what has been happening on the project at Ovingham, we have made some good progress on site even though the weather has been against us somedays, we have been working hard on the upstream cofferdam over the past month, this is an enclosure built within a body of water to allow the enclosed area to be pumped out or drained which then creates a dry working environment so that the work can be carried out safely. we have excavated it to formation level, Installed the stone, as well as installing concrete blinding, rebar and concrete base. Going forward over the next few months this we will be carrying this same operation to install the downstream cofferdam and concrete base. We are also using our crane to assist NWG with the pump replacements.
In the meantime if you have any issues or questions please leave a comment below or use the details provided to contact us and one of the team will be happy to help.
thanks
Julie
Please Login in order to comment on this update.
Morning all,
We wanted to let you know we will be working this weekend on site, on the 1st/2nd of March.
If you have an issues or queries please contact Jason our site agent on 07970248988.
Thanks.
Please Login in order to comment on this update.
Good morning all,
Can you believe January is nearly over, I hope you are all looking forward to 2025.
We would just like to welcome you to the first update of the year here at Ovingham. Due to the weather conditions progress has been slow on site but we are hoping the weather will improve so we can continue with the project. At the moment we are currently on with the installation of upstream concrete base unit for the first set of screens to sit on at the front of the river. Upon completion of the upstream concrete base we will then progress to the downstream concrete base for the second set of screens to sit on.
We would once again like to thank you for your continued support and patience while the works are ongoing, in the meantime if you have any questions or queries please leave a comment below or contact us using the details provided and one of the team will be happy to help.
Thank you
Julie
Please Login in order to comment on this update.
Good afternoon,
Can you believe its only 1 week to Christmas, where has this year gone,
We would like to provide the final update of the year for the Ovingham project before the Christmas break. The team are continuing working hard on making concrete bases for the new Eel screens that we are fitting into the River Tyne, this is the main focus for the up coming months as we need to get these completed so we can progress with the project.
Thank you all again for your patience and continued support while the works continue. If you have any questions about the project or any issues please feel free to leave a comment below or use the details provided to contact us and one of the team will be happy to help.If you require any assistance over the Christmas break please use the following contact number 0345 717 1100.
On behalf of Northumbrian Water and MMB we would like to wish you all a very Merry Christmas and a Happy New Year
Thanks again
Julie
Please Login in order to comment on this update.
Good afternoon,
As christmas draws closer I would like to welcome you to your monthly update, here on Ovingham Eels project.
We are making good progress on site, the team are now working hard on making concrete bases for the new Eel screens that we are fitting into the River Tyne, going forward over the next few months this will be their main focus on getting these completed so we can progress with the project.
We once again would like to thank you all for your patience and continued support while the works continue. In the meantime if you have any questions about the project or any issues please feel free to leave a comment below or use the details provided to contact us and one of the team will be happy to help.
Thanks again
Julie
Please Login in order to comment on this update.
Afternoon,
We just wanted to let you know we will be carrying out some work on site this weekend, the 21st & 22nd September.
Any issues please contact our site agent Jason on 07970248988.
Thanks.
Please Login in order to comment on this update.
Good afternoon, All,
hope you are getting ready for the Autumn
Just thought I would touch base with an update of the works in your area.
You will be pleased to know that the drilling at Ovingham has now finished and the team are now working on making concrete bases for the new Eel screens that we are fitting. This will be their main job for the next few months.
We hope we are not causing any major disruptions while the works have been progressing and we thank you for your continued support. If you have any questions or queries please leave a comment below or use the contact details provided and one of the team will get back to you.
Thank you
Julie
Please Login in order to comment on this update.
Morning all,
We wanted to let you know we will be working this weekend on site, on the 31st August/1st September.
If you have an issues or queries please contact Jason our site agent on 07970248988.
Thanks.
Please Login in order to comment on this update.
At Northumbrian Water, we work to make a difference in your community.
Have you considered a career that can help you do the same?
As well as the teams you see working in your streets, we have people doing a wide range of jobs that support that work to deliver the best possible water and sewerage services across the North East.
You can find out more about careers with Northumbrian Water and check out the latest vacancies by following the link below.
Please Login in order to comment on this update.