Update by Joan Tatters
Good Morning,
It's been a while since the last up date so i thought I'd give you a brief overview:-
- We have moved into the new grounds "Wylam Pumping Station", this really has created a lot more space for the team as the next phase of planned work The Eel Screens will require us to create more room for subcontractors to conduct their work along side us.
- There has been some cutting back and trimming of some trees to enable us to have access along the river bank, logs have been cut and returned to the landowner.
- Contractors have been working with us on pump 4.
- The ducting and chambers are now complete.
- The surge vessel has now bee installed in the field adjacent to the works.
- Please note there will be a building erected around the surge vessel in the coming weeks.
As the recent weather has been kind to us we have been able to move on quite significantly.
I've attached some photos of the recent works for you to have a look.