Good afternoon everyone, as the site team head of for a well earned Christmas break, I would like to summarise a year end project update.
The project is broken down into three distinct sections :
Carr Hill Inlet Pipeline
Some may recall we broke these works, Sandy Lane / Galloping Green Road to Bowes Incline railway line into three phases:
Phases 1&2 have not ran to plan, we were due to complete this section in December, we have encountered difficulties with our pipe supplier, pipes are now on site, these two phases will commence when we return to site on the 2nd January 2024, it will take a few days to implement the works in this area therefore look out for the traffic management that we will have in place.
Phase 3, the trunk mains connection for the new inlet pipe, you may recall was planned for the 3rd January 2024, this would of involved the closure of Sandy Lane / Galloping Green Road junction, again this has been postponed mainly due to ongoing operational issues further afield within our strategic water network, undertaking the proposed works at this location was deemed too much of risk, therefore these works will be rescheduled on a date to be agreed sometime in 2024, we will ensure that everyone is made aware of this revised date.
On a more positive note, the tunnel beneath the Bowes Incline Railway was completed we will complete the new pipe insertion early in January 2024.
Springwell Reservoir
You may of noticed if travelling along Mount Lane that the reservoir is starting to take shape, thanks you everyone for your patience and understanding whilst we undertook the bulk excavation, we broke up 60,000 cubic metres of sandstone rock and led it away from site to Springwell Quarry, over a period of eight weeks this equated to at its peak 180 vehicle movements a day to and from site, dust and mud dependant on the weather was and remains a challenge to our site, a combination of mitigation measures, dust suppression, wheel wash and road brushing will remain through the remaining construction period.
Reservoir wall erection to the east and northern aspects of the site as you will have seen are slowly being installed, from the bottom up, the deep reservoir sump and now underground control building and outlet chambers are slowly being constructed, this will eventually be a two storey below ground structure, steel fixing and concrete floors pours are well underway.
Inlet / outlet pipes to the reservoir are being designed with implementation of these works expected in the spring of 2024, look out for a notification in early 2024 of a road closure to allow these pipes to be laid through Mount Lane.
Springwell - Pikes Hole Pipeline
Works have progressed at pace on this section, land to the south of the compound where the new outlet pipe is to be laid has been fenced off and topsoil is being stripped, as has the land to the east of Springwell road where we have formed a temporary access route, in these areas we have resident archaeology watching briefs being undertaken by Durham University, we are working closely with Tyne & Wear County Archaeologist on the areas of interest and mitigation measures before the pipelaying commences.
Elsewhere along the pipeline route, in early 2024 we will be constructing access routes either side of Pearth Hall Road, look out for notifications of temporary road closures in 2024 whilst we lay the pipe through both Springwell Road and Pearth Hall Road (not at the same time). From Pearth Hall Road, the pipeline will hug land to the Northern edge of the A194 before crossing beneath the A195 finishing in and around Waterloo Road.
In summary, overall we are currently on programme to complete and have the new installations up and running by March 2025, followed by land restoration throughout the site.
Once again thank you everyone for your patience and understanding in 2023 as well as the year ahead whilst we undertake these works.
The site will be closing today returning on the 2nd January 2024, we will have security cameras operating throughout the site over the Christmas break as well as an our of hours emergency site contact telephone number 07970 173587.
Have a great Christmas and New Year.
Many Thanks
Richard Johnston
Project Manager