WATER NETWORK IMPROVEMENT
CURRENT WEATHER
0°C

Springwell Enhancements Project

Northumbrian Water proposes to construct a new underground service reservoir on land it owns off Mount Lane, along with related pipe work in the local area, in a £56m project to commence Spring 2023, following preparatory work on site. The proposed project will not only make the water supply to customers in Springwell Village and the surrounding areas more secure, but will also enable us to support the wider Wearside and South Tyneside areas with a more reliable and resilient water supply for many years to come. The reservoir would strengthen and future-proof the company’s existing network in the area, providing storage for around 50,000 properties in South Tyneside. In addition the new reservoir will enable us to provide improved resilience to the water networks to the east of Springwell Village, benefiting a further 200,000 properties in South Tyneside and Wearside.

Project updates

Update by Sarah Jayne Parvin

Good afternoon, We committed to providing weekly updates on this section of works. Currently, all previously shared information remains unchanged. Preparations are underway to carry out the testing for Test 2, which is now likely to take place towards the end of next week. We will provide a further update on Friday with details of any progress made.

We would like to clarify that the section of the Public Right of Way (PROW) between the stables and the Mount Community Centre remains closed. Unfortunately, our previous update did not make this clear, and we apologise for any confusion this may have caused. We will continue to provide updates on the status of this closure as the works progress.

Thank you for your continued patience and understanding as we move through this important phase of the project.

Sarah

Please Login in order to comment on this update.

Update by Sarah Jayne Parvin

Hello everyone,

As promised, here’s an update on our progress across the project areas. Please see below for details on each section:

Eighton Banks

As part of the ongoing improvements to the Carr Hill West pipeline, pipeline testing is ongoing which has highlighted repairs are necessary to parts of the pipeline, these repairs are located in and around the public rights of way.  For everyone’s safety, temporary footpath closures will be required, please note whilst we undertake this work we will maintain an open footpath at all times as indicated in this plan (click here)

Key Dates and Footpath Closures

  1. Section 1 : Scheduled to start on Monday, 11th November and continue for at least three weeks. 
  2. Section 2: we will advise on the dates for this repair 

After these tests, we will carry out a final test on the section from the Public Right of Way near the community centre up to the car park. This is planned for the second week of December and is critical for water flow through the pipeline. We’ll post weekly updates as testing progresses to keep everyone informed.

Peareth Hall Road

Pipeline installation from Springwell Road to Peareth Hall Road is complete, and we are now restoring the land. We aim to demobilise the temporary site compound off Peareth Hall Road before the Christmas break.

Additionally:

  • A194 rock scaling works will begin on 18th November now that we have formal agreement with Highways England.
  • This allows us to recommence pipelaying work on the Public Right of Way off Peareth Hall Road, this will begin on 2nd December, with completion expected before Christmas.

The Reservoir

At the reservoir site, we reached a significant milestone with the placement of the final wall panel this week. We have two final roof concrete pours left to secure the structure:

  • The next roof pour is scheduled for 12th November.
  • The final pour is planned for the week commencing 9th December.

Thank you for your patience and understanding as we carry out this essential work. We’re working to minimise disruption and will reopen paths as soon as it’s safe. For more details, please refer to the updated maps and diversion routes on the portal or reach out to our team with any questions.

 

Please Login in order to comment on this update.

Update by Anya Lowes

Good afternoon everyone,

We wanted to update you on the situation regarding our ongoing closures.

We appreciate your patience and understanding as we navigate these challenges. Our team is committed to addressing the current delays and ensuring the project progresses smoothly.

First, with regards to signage, we have again installed replacement permanent waterproof signs, as those that we had put in place have repeatedly been removed by unknown third parties.

We will look to give an update next week on the current National Highway approvals required to progress works in this area, and on other questions posed, to ensure we can give a full response to your queries.

Best regards,

Anya

Please Login in order to comment on this update.

Update by Sarah Jayne Parvin

Afternoon All, a quick note to let yet know, our final floor concrete pour is happening tomorrow. As with all the other floor pours, power floating will take place throughout the evening into the early hours.

 

 

Please Login in order to comment on this update.

Update by Sarah Jayne Parvin

We apologise if you're experiencing no water or low pressure. A technician is on their way to investigate the issue. Depending on what caused the interruption, we can usually fix this within two to three hours. As soon as we have more information, we'll be back in touch with an update.

For more information and updates visit 

Check your area (nwl.co.uk)

Please Login in order to comment on this update.

Update by Sarah Jayne Parvin

Good afternoon All, just a quick note to advise that Wednesdays base concrete pour was cancelled due to the wet weather. This has been rescheduled for Monday 30th September, as with all other floor pours, this will be power floated into the night.

Our next roof pour is also scheduled which will take place on Tuesday 1st October, the roof pours dont need powerfloating, so these will be finished during normal working hours.

Also a reminder we will be working this Saturday on the reservour site carry out steel fixing.

Thanks

Sarah

Please Login in order to comment on this update.

Update by Sarah Jayne Parvin

We’re pleased to inform you that the Peareth Hall Road and footpath closure's will be removed by the end of the school day today, Friday 13th September. Both footpaths will be available however we need to lay the final tarmac topping on each section, we will be completing this work on Saturday 14th September. One footpath will remain open while the other is worked on, then we’ll swap over.                                    

We will need to revisit the area in Spring 2025 to carry out the permanent tarmac topping 15 metres either side of the pipe trench as required by Sunderland City Council. This will be done under temporary two-way traffic lights, the footpaths will remain open, so pedestrians won’t be affected. We will advise closer to the date when these works are to be undertaken.

Over at Eighton Banks, you may notice little activity at the moment. We are preparing to test the pipe laid between the west side of the reservoir and Galloping Green Road. Testing is scheduled for the end of next week, with reinstatement work to follow, aiming for completion in early November. The main pipe connection outside the Waggon Inn pub is planned for early 2025 and will take around 8 weeks. We recognise the work has taken longer than expected and want to give the area a break in the lead-up to Christmas.

At Mount Lane, work on the reservoir continues. The eastern compartment is nearing completion, and the western compartment is about 60% finished. Backfilling at the north of the reservoir site is underway, compacting the material may cause some localised vibration in the surrounding area.

Please also note that work will take place over the next two Saturdays, focused on steel fixing on the roof. The noise will be minimal as no heavy plant movement is required.             Additionally, our next roof concrete pours are scheduled for 16th and 23rd September these will be carried out during normal working hours.                                                                   A concrete floor pour is expected on the 25th September which will require power floating into the early hours

Thank you for your continued patience and support as we complete this work.

Thanks 

Sarah

Please Login in order to comment on this update.

Update by Richard Johnston

Good evening everyone,

Works within the Peareth Hall Road closure have progressed well since last week's update.

This week, a temporary pedestrian/cyclist access through the closure will be maintained from Tuesday to Thursday at peak times, between  07:45 - 09:15 & 15:00 - 16:15.

We plan to fully reopen the road and one of the footpaths this Friday evening, following on with restoring the second footpath soon afterwards.

We will continue to keep you regularly updated and thank you for your continued patience. 

Richard Johnston

Project Manager 

Please Login in order to comment on this update.

Update by David Mortemore

Good afternoon everyone - A reminder that the Northumbrian Water Spingwell Reservoir Team are at Spingwell Community Venue today until 7pm, if you have a questions or would like an update on the project, please come and meet us. Hopefully see you soon. 

Please Login in order to comment on this update.

Update by Richard Johnston

Hello Everyone,

As indicated last week we will have a temporary safe pedestrian/cyclist route constructed through the road closure for the start of the new school term tomorrow, Thursday 5th September.

Whilst our pipelaying works continue in this area the temporary footpath will be operating on a peak time basis.

The safe access route will be open and monitored by our site staff from the morning of Thursday 5th September through the weekend (where our work will continue) into the evening of Monday 9th September, taking into account some of the comments we received, the access route will be available from 07:45 - 9:15 and again in the afternoon 15:00 - 16:15. The temporary footpath will not be accessible outside of these timescales.

We will update further on site progress next Monday on arrangements for the rest of the week.

Again, Thank you for your continued patience whilst we undertake these works.  

 

Richard Johnston

Project Manager

Please Login in order to comment on this update.

Work in your Community

Work in a business that supports your community

At Northumbrian Water, we work to make a difference in your community.

Have you considered a career that can help you do the same?

As well as the teams you see working in your streets, we have people doing a wide range of jobs that support that work to deliver the best possible water and sewerage services across the North East.

You can find out more about careers with Northumbrian Water and check out the latest vacancies by following the link below.

www.nwl.co.uk/careers