Good afternoon,
Some of you may have already seen that we have had to extend the traffic management this morning from Front Street down onto the A167 northbound carriageway, This is to enable the site team to continue works on the rising main. We anticipate this section of work to take 3 weeks to complete. There is a contraflow system in operation on the A167 to maintain traffic flow and the bus stops all remain operational in their usual locations.
We have also been instructed by Durham County Council to carry out our works across 7 days a week with immediate effect. This will continue until further notice.