Update by Katie Burdon
Portal Update WE. 9.11.18
The 90mm open cut started on Dalton Street on Monday 5th November and will progress through the week.
The reinstatement has started on the 90mm open cut on Corbridge Street and the under pressure tee is planned for Thursday 15th November (pm).
A sample has been taken at Corbridge Street (NE08) on Friday 9th November prior to connections next week.