Good Morning
Just a quick update on the Killingworth area of this scheme in that our works on Salters lane have been completed 1 day earlier than anticipated so we will be able to start at Bamburgh Road (Palmersville Chippy) 1 day earlier than planned, this is for a duration of up to 3 weeks.
Kind Regards
Kevin Mcgargle
Site Manager.