Update by Joan Tatters
Good Morning All,
I thought I'd let you know about what is happening regarding my last blog.
Yeah, we were due to start last Monday to complete the reinstatement along Denton Road and I am sure you will have received the letters comfirming it, however Michael and his team were delayed in completing other works at Keilder in Northumberland. I guess it was inevitable there would be a delay as the site restrictions and government guidelines being adhered too as a result of COVID-19.
Our apologies in the delay, the duration of work is still expected to be three weeks and will commence today so you will see some activity this morning. Again we ask to respect the social distance guidance should you be in the area for your daily exercise.
Please stay safe.