GENERAL PROJECT
CURRENT WEATHER
11°C

Wooler Water Treatment Works

As part of our ongoing investment programme and to ensure the highest level of customer service, we are constructing a new Water Treatment Works (WTW) at Wooler, Northumberland. The new WTW is located in the town of Wooler, at a site opposite Berwick Road Industrial Estate . The main construction phase commenced in summer 2020 and was substantially completed in autumn 2021. Final commissioning to bring the new WTW into service is currently scheduled to run through until autumn 2022.

Project updates

Update by Joan Tatters

Good Morning,

Before this second lockdow kicks in I thought I'd send you some photos of the work from last week. Unfortunately I won't be around for the next month (for obvious reasons) but please feel free to contact me. Gary and the team will continue working on site, being key workers, so if you see them when you are out and about please give them a wave.

 

Please Login in order to comment on this update.

Update by Joan Tatters

Morning All,

Sorry I didn't get an update on last week I was on holiday, however here we go for this week:-

Treatment Building          -         You will have seen the steel frame is shooting up and the roof is almost complete. All the grouting is complete to the column work and the bricklayers have started the block work.

Contact Tank                    -         The team are just doing the finishing touches to the upstand and the security covers are just about complete. The subbies are now preparing the water proofing..

WW Settlement Tank       -          Now in a position to start filling it with water for testing.

Industrial Estate              -          Tarmac work will commence tomorrow as well as long the B6525, 135 linear metres. The manhole will be installed and we can break into the existing one for connection and we will continue with the pipe work again along the B6525 and the traffic lights have and will continue to move along accordingly.

A massive amount of progress over these last two weeks and I have got to say the new Treatment Building looks impressive.

Thanks again for your patience and understanding whilst we have the traffic lights on, we do appreciate it. Please feel free to ask us any questions you may have.

 

Please Login in order to comment on this update.

Update by Joan Tatters

Good Morning,

Well last week was all stations go to be honest............

Treatment building: - The 2nd half of the slab was poured with 127m3 of concrete on Wednesday. The steel frame was erected on the Friday on the south side, its starting to take shape.

Contact tank: - Great collaborative work with our team and the subbies, between them they installed the cable conduit between the upstands on the roof, completed all the steelwork on the roof onThursday and all internal riser pipework and bellmouths in the channels.  

Washwater Settlement Tank: - The shutters were placed for the wall stitches and pipework. On Thursday further concrete was poured to finish the tank for further shutter work Friday.

Access road:-  All remaining kerbs were complete for the tarmac on Thursday/ Friday followed up by the white linning.

Well that was a week!

Please feel free to ask us any questions you may have, we would be happy to answer them. 

Please Login in order to comment on this update.

Update by Joan Tatters

Hello,

Just to let you know of the change of entrance to the site, we need to remove the temporary arrangement now.

The local council was out yesterday checking everything was in place and correct for the highway standards so we are good to go. Tarmacing will take place Thursday and Friday this week which means the traffic lights will remain for a little while longer.

Watch out for the steel work for the new building being erected later this week too, I will of course keep you posted.

I am out and about today if you want to say hello!

 

Please Login in order to comment on this update.

Update by Joan Tatters

Good Afternoon,

This week you may notice the team are working near to and within the farmers field adjacent to the site, the local farmer kindly agreed for us to use part of the land for storage as the pipe works progress. A huge THANK YOU from us.

There are some planned excavations into the industrial estate this week however it's likely to be the latter end of the week, I will of course confirm later.

Just a gentle reminder once again about the 2 way traffic lights please be that little more vigilant.

Thanks again for your co-operation 

Please Login in order to comment on this update.

Update by Joan Tatters

Good Afternoon,

Just a quick update this week...

The team are moving on with the work in this great weather and by now you will have noticed the traffic lights on the B6525 outside the industrial estate at the north end are on to ensure your safety. They will be for another 8-10weeks whilst we excavete for the raw and potable pipes to the water treatment plant.

Have a lovely weekend, don't forget if you want to ask any questions please feel free.

 

Please Login in order to comment on this update.

Update by Joan Tatters

Hi,

This weeks update..........

The team worked until 7pm on Saturday evening to make sure the trial holes were all done for Monday. I understand the tarmacing will be complete today and the lights removed.

Site

Treatment Building - The installation of the pipe work within the main area continues, including the ducts, pipes and drains in the North West corner. More in depth work has continued to fix the shutters to the slab and further shutters onto the cable pit ready for the pouring of concrete. (photo)

 Contact Tank: - Finished part of the base for the main channels and a concrete pour plusP started fixing the steel to the wall stitches. (photo)

Washwater Settlement Tank: - Continued with the works within the chamber, making it ready for backfilling of the intermediate slope base slab in the west chamber.

Pheww...confused?????...........here are some photos to help!

Stay safe and thank you again for your patience.

Please Login in order to comment on this update.

Update by Joan Tatters

Good Morning

Hope you had a great long weekend.

The road signs are now complete including the 30mph one at the north end of the B road and all is back to normal there. Whilst the weather last week wasn't great, Gary's team have cracked on and are still on programme.

Just a gentle reminder the 3 way traffic lights will go on Friday 4th until Monday 7th Sept across the B6525, so please be that little more vigilant. The trial holes shouldn't take much time and those businesses into the Industrial estate please don't worry should you need access over the weekend our guys will be working, so should you need to approach them for assistance please feel free, social distancing of course.

Don't forget if you have any questions about the project please ask away.

 

Please Login in order to comment on this update.

Update by Joan Tatters

Good Afternoon,

Hope storm Francis isn't causing too much problem to you all.

I've been out and about again (yes why oh why in this weather) just to let the industrial estate businesses know about our intentions for next week.

On Friday 4th September we will be conducting trial holes in the industrial estate to help us determine the road and ground conditions for the new treatment works. This work will take place on the junction of Redpath Tyres and McLaren Engineering and whilst we will be working on the B6525 at the same time we will be introducing traffic lights which will remain in operation until close of business Monday 7th September.

Working over the weekend has been a conscious effort to hopefully lessen the impact to all the surrounding businesses during this work.

We will however need to continue working within the estate for approximately three weeks heading towards the river to install the mains water pipe. Whilst our presence will be obvious, we will endeavor to keep our impact to a minimum.

We would just like to reassure you that access to the industrial estate will always be maintained and the water supply to your premises will not be affected during this time.

Don't forget if you want to ask any questions about the project please feel free.

 

Stay safe.......

Please Login in order to comment on this update.

Update by Joan Tatters

Good Morning,

Well, Monday was a wet one and I managed to catch up with some of you whilst confirming the traffic light arrangements.

I just thought I'd just add a few more photos as sometimes you just don't need words !

 

PS, love the fountain in the town

 

Please Login in order to comment on this update.

Work in your Community

Work in a business that supports your community

At Northumbrian Water, we work to make a difference in your community.

Have you considered a career that can help you do the same?

As well as the teams you see working in your streets, we have people doing a wide range of jobs that support that work to deliver the best possible water and sewerage services across the North East.

You can find out more about careers with Northumbrian Water and check out the latest vacancies by following the link below.

www.nwl.co.uk/careers