Update by Gabrielle Ward
Good afternoon,
I hope you're well, and have been enjoying this lovely weather!
In our last update I mentioned that 596m of pipeline had been welded together ready to be installed in the Rockwill Development. The team have now installed 140m of this pipeline using a method called directional drilling. I have mentioned drilling in most of my updates, but just in case you were wondering how this works; Directional drilling is less intrusive than digging a trench, and involves digging chambers either side of where the pipe will be laid and feeding the pipe underground from one chamber to the other.
We will be carrying out some trial holes on the verge of the A67 on Wednesday 28th June to try and locate a gas main. We don't anticipate this to cause any disruption to road users and pedestrians however, if you do require any assistance our team will be happy to help.
You will have now seen our working area set up in Lartington Way. The top soil has been stripped, and the stone has been laid ready for welding this section of pipeline. We appreciate this area is popular with dog walkers, so as a little thank you for putting up with us, the site team have created a 'doggy station' for our four legged friends to enjoy some treats and water. We've had plenty of visitors and the lads have loved meeting you all!
Finally, we just wanted to let you know that we will be starting to lay pipeline in Egglescliffe School Field from late July. The team have commenced setting up our working area. We will initially be accessing this area via Lartington Way, and then as work progresses, we will be accessing this area from Durham Lane adjacent to Allens West.
As always, if you have any questions please feel free to leave a comment below and a member of the project team will get back to you.