Update by Anthony Birkett
Hi Everyone
I've been in touch with Darren from site for an update on progress this week.
As you've probably seen, we've now permanently reinstated the Northern half of Wood Vue (nearest the Cow Plantation). We thank you for your patience while we completed this work earlier this week. We will now continue up the road, moving the rolling road closure as we go.
Work has also been progressing in the Cow Plantation - I've attached a picture of the Combined Sewer Overflow(CSO) we've been working on - this is designed to help reduce the risk of flooding in the future. We will continue working on this next week.
I will be in touch with those directly impacted by our work in the coming weeks
Regards
Tony