The construction phase of this project is now complete.

There may still be updates, so the project will remain here. We are still monitoring the project and will reply to any comments. So if you have any questions please feel free to comment or contact us here.

GENERAL PROJECT
CURRENT WEATHER
5°C

Fenham

We are investing £2.2 million to improve the water supply in the west end of Newcastle.

Update by Sarah Jayne Parvin

Good afternoon hope you are well.

The resurfacing work on Linden Avenue went ahead as planned on the 22/23rd October.

Work is progressing well on site and we are planning on removing the 13t excavator via the gates at Linden Ave. the excavator needs to exit via Linden Avenue, which is planned for tomorrow 18th November. Once this is out then we can continue with replacing the gates with palisade fencing, this will start the following day 19th November.

Over the next few weeks, we will be removing the cabins off site, these will exit via West Road entrance, following that we have reinstatement work on site to finish before we are complete and demobilise.

We would like to thank you for your continued patience and understanding while we carry out these essential works.

If you have any questions or feedback, please get in touch at Sarahjayne.parvin@JNBentley.co.uk or use the contact us link at the top of this page,

Thanks

Sarah

View all updates
Work in your Community

Work in a business that supports your community

At Northumbrian Water, we work to make a difference in your community.

Have you considered a career that can help you do the same?

As well as the teams you see working in your streets, we have people doing a wide range of jobs that support that work to deliver the best possible water and sewerage services across the North East.

You can find out more about careers with Northumbrian Water and check out the latest vacancies by following the link below.

www.nwl.co.uk/careers