The construction phase of this project is now complete.

There may still be updates, so the project will remain here. We are still monitoring the project and will reply to any comments. So if you have any questions please feel free to comment or contact us here.

GENERAL PROJECT
CURRENT WEATHER
7°C

Fenham

We are investing £2.2 million to improve the water supply in the west end of Newcastle.

Planned work

THIS PROJECT INVOLVES CARRYING OUT MAINTENANCE AND CHANGING THE SHAPE OF ONE OF OUR RESERVOIR TANKS IN FENHAM. ONCE THE WORK IS COMPLETE WE WILL RE-LANDSCAPE THE AREA.

Our temporary site compound will be built within our reservoir site for the duration of the work. Due to the location of the site, our access route for construction traffic will be along Two Ball Lonnen, Cedar Road and Linden Avenue. A temporary haul road will be in place across the playing field to the rear of Acanthus Avenue while we work here. If you are going to be directly affected by this, our site team will contact you in advance of the work with further information. 

Please see our site plan for further details about the location of our site and access route.

This project will involve demolition and construction work in order to upgrade the reservoir tank and, as a result, we expect there to be increased levels of noise in the local area during January and February 2017. We will keep you updated closer to the time of this work about expected timescales.

Please be assured that we are working closely with our partners to do all that we can to minimise any disruption to you and your community throughout the work. 

Stage of work Start date End date Additional information
Construction of temporary access route across playing fields 23/11/2016 01/12/2016 Our temporary access route will be in place for the duration of this work
Construction of compound within reservoir site 02/12/2016 06/12/2016 Our compound will be in place for the duration of this work
Demolition work on reservoir tank 05/01/2017 22/02/2017 Further information about this work will be shared soon
Construction work on reservoir tank including landscaping 23/02/2017 04/07/2017  
Installation and testing of new equipment 08/06/2017 13/10/2017  


 

Work in your Community

Work in a business that supports your community

At Northumbrian Water, we work to make a difference in your community.

Have you considered a career that can help you do the same?

As well as the teams you see working in your streets, we have people doing a wide range of jobs that support that work to deliver the best possible water and sewerage services across the North East.

You can find out more about careers with Northumbrian Water and check out the latest vacancies by following the link below.

www.nwl.co.uk/careers