GENERAL PROJECT
CURRENT WEATHER
1°C

Fenham

We are investing £2.2 million to improve the water supply in the west end of Newcastle.

Project updates

Update by Sarah Jayne Vickers

Good afternoon, quick post to let you know we have a couple of deliveries next week, on Monday and Tuesday.

Any question please dont hesitate to contct us using the 'Contact' at the top of the page, or alternativly leave a comment below on this post.

Thanks 

Sarah 

Please Login in order to comment on this update.

Update by Sarah Jayne Vickers

Good afternoon, our latest update in October suggested we were expecting to remain on site until the end of November and demobilise the site for approximately 6 months, with an expectation to return in late spring to complete earth works and final tidying up.

These timescales have moved, and we can confirm that we will not be demobilising prior to Christmas as we still have some works to complete which are dependent on weather conditions. Once this work has been complete, we expect to leave end of January and return 6 months after our departure to construct some earth embankments and do some final tidying up. This may take up to three months to complete and will involve a significant number of vehicle movements. We will write to you again nearer the time to give you further information about our plans.

I’d like to take this opportunity to thank you for your patience and understanding while we have been carrying out our work and would like to wish you a peaceful Christmas and New Year.

Thanks

Sarah

Please Login in order to comment on this update.

Update by Sarah Jayne Vickers

Good afternoon, just a quick update to let you know we have a collection arranged through Linden Avenue gates tomorrow.

We would like to thank you for you continued patience and understanding during these works.

As always, any questions please don’t hesitate to ask.

Thanks

Sarahjayne

Please Login in order to comment on this update.

Update by Sarah Jayne Vickers

Good afternoon All, just to let you know we have two deliveries scheduled this week Wednesday and Friday through the gates at Linden Avenue. As always, we will have one of our team onsite to allow them to get on and off site.

Any questions please don’t hesitate to contact us using the ‘contact us’ at the top of this page.

Thanks 

Sarahjayne 

Please Login in order to comment on this update.

Update by Sarah Jayne Vickers

Good morning All, there are a few deliveries scheduled in for this week. These deliveries are expected on Wednesday 6th November one am and one pm and a further delivery on Friday 8th November pm.

Thanks for you co-operation and patience.

Sarah 

 

Please Login in order to comment on this update.

Update by Sarah Jayne Vickers

Good morning, 

There will be a diesel delivery Friday 1st Nov and on Monday 4th Nov through the Linden Ave access gates. The gate will be manned as usual during the delivery and the locked on completion.

Thank you for your patience.

Sarah

Please Login in order to comment on this update.

Update by Sarah Jayne Vickers

Good afternoon, we have a delivery due tomorrow morning and also further deliveries on Monday and Tuesday next week via Linden Avenue access.

Thank you for you patience.

Sarah

Please Login in order to comment on this update.

Update by Fenham Project Team

Good evening all, we want to make you aware of some deliveries due to site via the access on Linden Avenue. The deliveries are scheduled for Tomorrow and Monday, and although I cannot guarantee a time its likely to be in the afternoon.

There has been an increased number of vehicles attempting to access the gates at Linden Avenue in error, they were for another company within the local area.

Also please look out for a letter landing over the coming days with a project update.

If you have any question please don’t hesitate to comment below, alternatively us the 'contact us' at the top of the page for an email to be send to the project team.

Thank you for your patience during our works.

Sarah

Please Login in order to comment on this update.

Update by Fenham Project Team

Good afternoon,

I would like to give you an update about our work within the Fenham Reservoir site.

The work had expected to be finished before now and to have left the site. Some issues have been encountered and some further works need to be complete, which means we will be on site for longer than anticipated.

We will be working until mid-November 2019 when we will demobilise the site cabins and leave the site for approximately six months. We will then return to landscape the site and do some final tidying up.

I’d like to thank you for your continued patience whilst we have been working on site.

If you have any question please comment below or alternatively use the contact at the top of this page.

Thanks

Please Login in order to comment on this update.

Update by Fenham Project Team

Hello

Following our most recent post we are expecting a site delivery accessed via Linden Avenue on Friday 9 August 2019. If the unlikely event of any delay this delivery will be rescheduled for Monday 12 August 2019. 

When we have information on further dates, we will of course update you.

Best wishes

The Project Team 

Please Login in order to comment on this update.

Work in your Community

Work in a business that supports your community

At Northumbrian Water, we work to make a difference in your community.

Have you considered a career that can help you do the same?

As well as the teams you see working in your streets, we have people doing a wide range of jobs that support that work to deliver the best possible water and sewerage services across the North East.

You can find out more about careers with Northumbrian Water and check out the latest vacancies by following the link below.

www.nwl.co.uk/careers