Update by Sarah Jayne Parvin
Good afternoon, time for the first update of 2023!
Groundwork civils are progressing well with the final foot path around the MCC unit to be poured this week.
Auto de sludge pipe work and concrete base to be complete targeting end of February and we will commence the installation of the electrical side of the project in the coming weeks.
The team are now preparing for the installation of the MCC kiosk and the electrical works, with a view to install the above ground mechanical work once the delivery and installation of the MCC panel is complete towards the end of March.
We have included a couple of pictures below which show the work carried out this month.
If you have any questions, please comment below and one of the team will be in touch.
Sarah