Update by Sarah Jayne Parvin
Good afternoon, we are pleased to provide you with an update on the progress of our recent activities. In the past few weeks, we have completed several important tasks, including the Auto de-sludge pipework, ducting and duct chambers, and commenced the auto de-sludge slab. We have also completed the access track to the storm tank, including kerbs, and the footpaths for MCC, along with regrading the ground.
We have several planned activities for the coming month, including the installation of MCC and wash water kiosk with metalwork and MCC panel. We will also be completing the auto de-sludge area, installing penstocks, and benching the inlet works, including wall construction at screen 2.