Good morning,
I hope you're all well?
Since our last update, work has continued to progress well on site. The MCC Kiosk and internal panels have successfully been installed. The wash water kiosk has been installed and the pipework and connections to the wash water kiosk will be carried out in the upcoming weeks. The electrical work to site is now underway, along with the benching works to the inlet channel 1.
Completed work since our last update is as follows:
- Auto de-sludge pipework
- Cresswell Flowmeter pipework
- Wall thickener for screen 2
- Benching to inlet channel 2
I will be posting another update in a few weeks time. If you have any questions, please feel free to leave a comment below and a member of the project team will get back to you.
Have a great week, and a lovely Easter.
Thanks.
Gaby