Update by Paul Davison
Good morning,
You should have received a letter last week to let you know that we were planning to start site on Monday 25th July.
Due to unexpected long lead in times for critical electrical components which we will need for our new electrical control panel, we have revised the programme slightly to ensure we can deliver the upgrade works as efficiently as possible and in the process, reduce any disruption to customers. As a result we have taken the decision to delay the construction start until the Monday 15th August and subsequently, this will push the completion back to early June 2023.
Kind regards