Murton Flooding

Together with our supply partner, ESH-MWH, we have undertaken a detailed study of the sewer network to establish the cause of flooding in the area. We want to keep you informed about our investigations and work we are considering in the Woods Terrace area.

Project updates

Update by Christine Taylor

Hi

As I mentioned last week the winners of our poster competition visited site on Friday.

It was great to see them all, both staff and pupils are a credit to St Jospehs RC School.  Brilliant artwork from each of our winners.

The posters are currently displayed on our fencing and will be until the end of the project.  If you are in the area please take time out to have a look.

Thank you once again Jasmine, Zoe, Kate and Sophie for your posters, and the staff for taking the time to visit us.

Christine

 

 

Please Login in order to comment on this update.

Update by Christine Taylor

Hi

We are very excited at Murton today as we are expecting VIP guests.

Our competitions winners from St Joseph RC Primary School are visiting site to see their poster displayed.

I will be posting photos next week of the visit.

Have a great weekend

Christine

Please Login in order to comment on this update.

Update by Stephen Bennison

Hi everyone,

It's time for the weekly update again, things are going well with digging out for the storm tank and the weather has been a great help with this.The site team have made a decision to work this saturday morning to take advantage of the weather and enable us to finish digging out a little earlier than expected. We won't have wagons coming in and out of the site though so any disruption will be minimal and no works will be carried out after 14.00 hrs. We really appreciate your patience and understanding while we carry out these works. And as with the tank all other parts of the scheme are continuing to progress nicely.

hope you all have a lovely weekend

Steve

Please Login in order to comment on this update.

Update by Christine Taylor

Hi

I thought I would take a moment to share a photo of our Contracts Manager Dave Player.  He was originally on our team but seemed camera shy. 

Not anymore, please see attached photo.  As previously stated, Dave will be on site regularly and is always happy to help.  Please feel free to go and see him for any assistance.

On another note, I was on site on Friday afternoon speaking to a few residents about the area where we have our compound.  Just to put all your minds at ease we will reinstate the area when we leave site.

Thanks

Christine

Please Login in order to comment on this update.

Update by Stephen Bennison

Hi everybody,

well the sun is shining, could summer be here allready? lets hope so. I just wanted to give you an update on our progress this week. we have now finished installing the sheet piles so you should notice a significant difference in noise levels from now on. Next week we will be starting to dig out for the storm water tank so you may notice the number of wagons in and out of site will increase as we carry out these works. The drainage works at the rear of woods terrace continue,and this is going well.

lets hope the weekend is as nice as the week has been so far and enjoy it everybody.

steve

Please Login in order to comment on this update.

Update by Stephen Bennison

Afternoon everybody,

As mentioned last week we have now started installing the temporary works (sheet piles) for the storm tank, you may have noticed the massive piling rig within our work area. This is going reasonably well and i hope it hasn't been to noisy for you all. we are continuing with the drainage works to the rear of woods terrace which is also progressing nicely.

hope everybody is looking forward to the weekend as much as me.

steve

Please Login in order to comment on this update.

Update by Stephen Bennison

hi everyone,

Just wanted to give you all a mid week update on our progress so far. As mentioned in my last update the drainage works have started this week although we are working at a steady pace at the moment due to the amount of existing services within this location. The works to form the working platform are now complete so the number of wagons going to and from site will be a lot less untill we start the tank excavation on the 6th March.  The next phase of the works is to install the temporary works for the storm tank, this will start on monday and involves driving sheet piles into the ground. This may be a lottle noisy at times but we will do all we can to keep this to a minimum. i will provide further updates as we progress.

steve

Please Login in order to comment on this update.

Update by Stephen Bennison

Hi everyone,

As mentioned in Christine's last post we closed a small section of the road to the rear of Woods Terrace on Monday, this gave us the opportunity to dig and locate existing services before we start installing the new drainage, which will start on monday 20th february. You will have noticed a high volume of traffic (mainly wagons) in and out of the site this week as we have been very busy establishing our site compound and setting up the site offices. This will continue again next week as we dig out the clay and replace it with stone to form a solid working platform. I will keep you posted with further updates next week.

Enjoy the sunshine this weekend everybody and maybe a BBQ ?

steve

Please Login in order to comment on this update.

Update by Christine Taylor

Hi

Just a reminder, as of Monday the rolling road closure will begin on the lane to the rear of Woods Terrace.  This will mean that small sections of the lane will be closed for short periods of time.  The rolling road closure will begin on the 13 February 2017 and completed a the north end of the road in June 2017. 

We will begin by closing the section of road on Monday 13 February, near to the junction of Western Terrace South.  The part of the works should be completed within 4 weeks, we will then progress to the next section.

Our site team will contact customers if they are impacted by the works.  We will strive to ensure access into garages etc as the work progresses, any problems Steve Bennison is on site and is more than happy to help.

Have a lovely weekend and we will see you next week.

Christine

Please Login in order to comment on this update.

Update by Stephen Bennison

Hi everyone,

Well we arrived on site on monday as planned and have started works to create our compound / site office area. we have now completed installing the permanent perimiter fencing to the site and have also cut down the three trees in this area to give us the working space required. We will keep you informed about the scheme as things progress with regular updates and information.

Enjoy the upcoming weekend everybody

Steve

Please Login in order to comment on this update.

Work in your Community

Work in a business that supports your community

At Northumbrian Water, we work to make a difference in your community.

Have you considered a career that can help you do the same?

As well as the teams you see working in your streets, we have people doing a wide range of jobs that support that work to deliver the best possible water and sewerage services across the North East.

You can find out more about careers with Northumbrian Water and check out the latest vacancies by following the link below.

www.nwl.co.uk/careers