Update by Anthony Birkett
Hi Everyone
I've been on site this morning visiting Mac, to see how we're getting on on Rosehill Road. Mac was very busy, making the necessary arrangements to pull ff site for Christmas. Its looking likely that we will have completed the work and permanently reinstated Rosehill Road by 20 December. We'll then be able to remove our cabins and plant in time for our Christmas shut down. Hopefully we'll have finished all reinstatements to the grassed area as well, but we'll need to confirm this nearer the time.
There is light at the end of the tunnel!
Regards
Tony