Welcome to your Community Portal

Key

General Project
Rainwise Scheme
Water Network Improvement
Eel Protection Scheme
Every Drop Counts
NIDP Flooding Project
General Wastewater

Latest Updates

By Rachel Rutter

6 Photos
Good afternoon, Can you believe the weather, hope everyone is wrapping up warm. This week the team and our contractor Retroflo have been continuing with cabling to various chambers and the MCC kiosk within Plawsworth and Pity Me Sewerage Treatment works. The insulation wrapping of external pipework at the valve chamber base including telecoms to the control building is complete. ESH have been drilling and dowelling exiting concrete slabs ready for the reinforced concrete reinstatement with Northumbrian Water facilities. Installation of the steel sleeve is complete to allow insertion of the gravity sewer. Please contact us direct if you have any questions at nwl.customer@esh.uk.com Thank you for your time Rachel

By Rachel Rutter

Good afternoon, Can you believe the weather, hope everyone is wrapping up warm. Following on from my previous update the pressure testing is now complete with a small amount of work required to our rising main pipeline from Longnewton to Goosebeck. Directional Drill works under/across Yarm Road have been complete; with preparation of the rising main excavation and installation ongoing from the water course back to Middleton One Row. Gravity drainage is now complete with the exception of one manhole, which shall be constructed following the guided auger bore works taking place next week. Please contact us direct if you have any questions at nwl.customer@esh.uk.com Thank you   Rachel

By Rachel Rutter

Good afternoon,  Installation of the new section of sewer into the existing Middleton One Row facility is complete. The road closure on The Front / Aislaby Road has now been removed and the road reopened. I would like to thank you for your patience and cooperation during our essential work.  Please contact us direct if you have any questions at nwl.customer@esh.uk.com Thank you for your time.  

By Sarah Jayne Parvin

Good afternoon, We committed to providing weekly updates on this section of works. Currently, all previously shared information remains unchanged. Preparations are underway to carry out the testing for Test 2, which is now likely to take place towards the end of next week. We will provide a further update on Friday with details of any progress made. We would like to clarify that the section of the Public Right of Way (PROW) between the stables and the Mount Community Centre remains closed. Unfortunately, our previous update did not make this clear, and we apologise for any confusion this may have caused. We will continue to provide updates on the status of this closure as the works progress. Thank you for your continued patience and understanding as we move through this important phase of the project. Sarah

By Julie Oakley

5 Photos
Good morning, Everyone, Hope you all enjoyed Halloween and Bonfire night, now its the run up to Christmas, just dont know where this year has gone! But on that note we would like to provide you with your monthly update on the treatment works here at Wark. Since the last update we have carried out the following. We have started to demobilise the site starting from our top compound to a smaller set up at the bottom section of the site and civilised the area where our cabins were located before. Flows have been turned through the new HST tank and all over pumping has been removed from site. We have began to reinstate the bottom of the site with topsoil and stone prior to leaving site before Christmas. We have carried out some work in the village to help the community with their parking issue and constructed additional car parking spaces, these are situated in front of the doctors surgery, and we have also helped reinstate a nearby car park with stone that was left over from the works.  Once again we would like to thank you all for your continued support and patience. In the meantime if you require any further information or you have any questions or issues please leave a comment below or use the details provided and one of the team willbe happy to help. Thank You  Julie

By Alice Blackett

10 Photos
Good Morning We are back with another update on our 5 Storm Tank Overflow projects. Moor Crescent/Barnard Avenue, Ludworth The team have continued to work on the large diameter tank over the last few weeks, even though the weather hasn’t been on their side and have been faced with delays due to uncharted services. The team are aiming to have the tank complete by Friday 22 November with the surface water separation of the sewer completed 2 weeks after if not before. Barnard Avenue road closure remains in place, with the team progressing well with the work and moving the road closure up to the next section. Etherley Dene, Bishop Auckland The team continue to work in the background until the urgent third-party work in the area is complete. Our aim is to make sure disturbance is kept to a minimum and will provide a further update when our work can begin. Pithouse lane, Leamside Installation of the new CSO is currently in progress. CSO installation works will be ongoing for the next few weeks. Finchale View, West Rainton We are currently installing the compound area on site. Over the next couple of weeks, we will be completing the compound and haul road installation and stripping the topsoil at the worksite ready for the drainage installation. Stanghow Road, Lingdale Excavation works for the new storm tank will be starting week commencing 18th November. This means there will be heavy load vehicles present and travelling along Stanghow Road. With this in mind, please can we ask drivers to drive carefully and take care to ensure everybody is kept safe. In addition to this, the speed limit will be reduced from 60mph to 40mph. We are happy to discuss any aspect of this works, please contact us at nwl.customer@esh.uk.com or click 'Contact Project Team' on this page. Thank you Alice & Rachel

By Bethany Oakley

Good afternoon all, Happy Wednesday! I thought I'd jump on and update you on the recent progress that has been made on Site. PS concreting works complete. The concrete to the chemical dosing path is nearly complete. The drain down pipework is also nearing completion. Aquazone/Forbes Tanks now in place. Intelect continue works and may take advantage of weekend working to continue with the great progress. As always, if there is anything that we can assist with further, please don’t hesitate to reach out or add a comment in the box below and a member of the Project Team will respond accordingly. Take care and speak soon, Bethany

By Rachel Rutter

Good morning  The roof slabs on the Carlow Tank were lifted on Monday 4 November, with the pour completed on Friday 8 November. Ducts have been installed and the team have begun digging the kiosk base. Temporary work will be removed in the coming weeks. All work is now taking place within the sewerage treatment works.  Please contact us direct if you have any questions at nwl.customer@esh.uk.com Thank you for your time. Rachel

By Julie Oakley

Good afternoon,  As christmas draws closer I would like to welcome you to your monthly update, here on Ovingham Eels project. We are making good progress on site, the team are now working hard on making concrete bases for the new Eel screens that we are fitting into the River Tyne, going forward over the next few months this will be their main focus on getting these completed so we can progress with the project. We once again would like to thank you all for your patience and continued support while the works continue. In the meantime if you have any questions about the project or any issues please feel free to leave a comment below or use the details provided to contact us and one of the team will be happy to help. Thanks again Julie    

By Julie Oakley

 Dear Resident. Just to make you aware from 8am Wednesday 13th November 2024 we are expecting a delivery of a 150T crane,  this is approx. 3 meters wide, and we will need plenty of room to manoeuvre. As you are aware the entrance to the site is very limited. Due to this issue could you please refrain from parking at the entrance of the access road to site during this period. We would like to thank you for your patience and your continued support while the works are progressing. Please be assured that your water and wastewater services will not be interrupted while this work is in progress and, as with all work of this type, progress is subject to weather and site conditions. If you have any questions or queries please comment below or use the details provided to contact us and one of the team will be happy to help. Thank You Julie

By Sarah Jayne Parvin

Hello everyone, As promised, here’s an update on our progress across the project areas. Please see below for details on each section: Eighton Banks As part of the ongoing improvements to the Carr Hill West pipeline, pipeline testing is ongoing which has highlighted repairs are necessary to parts of the pipeline, these repairs are located in and around the public rights of way.  For everyone’s safety, temporary footpath closures will be required, please note whilst we undertake this work we will maintain an open footpath at all times as indicated in this plan (click here) Key Dates and Footpath Closures Section 1 : Scheduled to start on Monday, 11th November and continue for at least three weeks.  Section 2: we will advise on the dates for this repair  After these tests, we will carry out a final test on the section from the Public Right of Way near the community centre up to the car park. This is planned for the second week of December and is critical for water flow through the pipeline. We’ll post weekly updates as testing progresses to keep everyone informed. Peareth Hall Road Pipeline installation from Springwell Road to Peareth Hall Road is complete, and we are now restoring the land. We aim to demobilise the temporary site compound off Peareth Hall Road before the Christmas break. Additionally: A194 rock scaling works will begin on 18th November now that we have formal agreement with Highways England. This allows us to recommence pipelaying work on the Public Right of Way off Peareth Hall Road, this will begin on 2nd December, with completion expected before Christmas. The Reservoir At the reservoir site, we reached a significant milestone with the placement of the final wall panel this week. We have two final roof concrete pours left to secure the structure: The next roof pour is scheduled for 12th November. The final pour is planned for the week commencing 9th December. Thank you for your patience and understanding as we carry out this essential work. We’re working to minimise disruption and will reopen paths as soon as it’s safe. For more details, please refer to the updated maps and diversion routes on the portal or reach out to our team with any questions.  

By Rachel Rutter

Good morning,  We would just like to take this opportunity to thank everyone who attended last night’s event. It was a pleasure for the Esh Stantec and Northumbrian Water team to meet with you and discuss the work taking place within the area.  For those who couldn’t make it or thought of a question after you attended and you’re looking for further information, please don’t hesitate to speak to a member of the site team or contact us direct at nwl.customer@esh.uk.com. Thank you, have a lovely weekend! Rachel
Work in your Community

Work in a business that supports your community

At Northumbrian Water, we work to make a difference in your community.

Have you considered a career that can help you do the same?

As well as the teams you see working in your streets, we have people doing a wide range of jobs that support that work to deliver the best possible water and sewerage services across the North East.

You can find out more about careers with Northumbrian Water and check out the latest vacancies by following the link below.

www.nwl.co.uk/careers