A quick update on the project for you, Ocean Park Attenuation Tank:- We have completed the third concrete roof screed pour with aid of a mobile concrete pump and are continuing on with the internal concrete benching operations of which there is quite a large quantity.
We have been able to carry out some perimeter backfill operations around the tank up to the roof height, and we are now placing the precast concrete turrets to bring up to our new proposed ground levels, works will continue into next week.
Boldon Flats new drainage network:- Junction of Moor Lane/West Meadows Road, We have completed the first half of the road crossing with the aid of three way traffic control signals also installed permanent tarmac reinstatement, the traffic management has now been switched over to enable the second half of the crossing to be installed, works will continue into next week.
Morrison's new drainage network Phase 2:- We have this week commenced at Cut throat Dene within the grassed area forming a new outlet and progressing towards Lowry Road.
Next week we are to commence the actual road crossing preparation works, where we shall be installing three way traffic signal controls at the junction, to the bottom end of Lowery Road.
Please be advised in advance that there will be congestion at this location, although we shall endeavor to carry out the works as quickly and as safely as possible.
We thank you for your patience, as we carry out these essential works.
Have a good weekend
Steve.