Update by Kevin McGargle
Good Morning
I just thought id give you a brief update with regards the works on the Great Lime Road area of the scheme as below:-
1. Palmersville Chippy - Yesterday we completed the wearing course reinstatement to the main highway (photo attached), we are now completing all of the final conections of the new water main laid and will be backfilling and reinstating the works area today/ tomorrow to be completed for friday night, the area will be seeded and cut tidy on completion.
2. Monday 10th march 2019 for a duration of 3 weeks we will be at Miller close to carry out works on Great Lime road (in the grass verge) installing a new main from where we previously worked at christmas west to the junction of wesley way, please note that we will have a lane restriction on the road and the fottway closed during these period, a suitable walkway will be provided to use.
I wil provide further updates as the works proceed.
Kind Regards
Kevin McGargle
Site Manager