The construction phase of this project is now complete.

There may still be updates, so the project will remain here. We are still monitoring the project and will reply to any comments. So if you have any questions please feel free to comment or contact us here.

GENERAL PROJECT

Lamesley Rising Main Replacement

To replace a failing pumping main from Lamesley Sewage Pumping Station to Birtley Sewage Treatment Works.

Project updates

Update by Rachel Rutter

Good morning,

This week the crew continue with the reinstated of the topsoil in the north field and Birtley Sewerage Treatment Works. The team continue to rotavate and seed due to weather conditions.

The work on Greenford Lane is ongoing and traffic management will remain in place until 11 August 2023 for the installation of the Rising Main.

Removal of the central compound and restatement works continue in the central fields.

Please contact us direct if you have any questions at nwl.customer@esh.uk.com or 0191 3774500.

Have a lovely weekend!

Rachel 

Please Login in order to comment on this update.

Update by Rachel Rutter

Good afternoon,

Last week the crew reinstated the topsoil in the north field and Birtley Sewerage Treatment Works. Within the next two weeks it will be rotavated and seeded, with the stone compound now been removed.

The work on Greenford Lane is ongoing and traffic management is in place for continuation of the installation of the Rising Main.

Please contact us direct if you have any questions at nwl.customer@esh.uk.com or 0191 3774500.

Thank you

Rachel 

Please Login in order to comment on this update.

Update by Rachel Rutter

Good morning,

This week the team have completed the pipework and chamber installation in the North Fields. The pipework has been tested and passed. The Stoned compound will remain, as access will be required when work commences at Lamesley Pump Station.

Reinstatement of the central fields and unearthing of field drains are ongoing and expected to complete WC 10 July 2023.

The excavation, installation and backfill of the rising main has been completed and the reinstatement is ongoing.

Please contact us direct if you have any questions at nwl.customer@esh.uk.com or 0191 3774500.

Have a lovely weekend!

Rachel 

 

 

Please Login in order to comment on this update.

Update by Rachel Rutter

Good afternoon,

I would like to take this opportunity to update you on the next steps of the upgrade to the sewer network. The road closure on Haggs Lane from Lamesley Road will be removed on Friday 16 June 2023. We appreciate that this is an extension to our original date, and we apologise for this and thank you for your continued patience and understanding.

On Monday 19 June 2023 3-way traffic management will be set up on Greenford Lane and Kibblesworth Bank for a period of 7 weeks, to complete the second section of the installation. As the installation moves past the junction this will be reduced to 2-way traffic lights while we complete the connection.

Please contact us direct if you have any questions at nwl.customer@esh.uk.com or 0191 3774500.

Thank you

Rachel 

Please Login in order to comment on this update.

Update by Rachel Rutter

Good morning,

Hope your all having a lovely week.

Over the last couple of weeks, the crew have completed the reinstatement over the archaeological area and completed the pipe work within the chamber for the North Field.

Within Haggs lane the excavation/installation and backfill of the Rising Main is ongoing with the road to be reinstated by 9 June 2023.

Reinstatement and installation of the field drains in the central fields are ongoing.

Please contact us direct if you have any questions at nwl.customer@esh.uk.com or 0191 3774500.

Thank you

Rachel 

Please Login in order to comment on this update.

Update by Becky Gartland

Good morning, 

I just wanted to take this opportunity to say hello and introduce myself as some of you may have seen me in the area this week. My name is Becky Gartland and I work alongside Rachel and Christine within the Customer Team for Esh Stantec. Having recently returned from Maternity Leave I am in the process of getting caught up with the ongoing work that has been happening in your local area and will be an additional point of contact should anyone have any queries or concerns. 

Whilst on site last week I have taken some photos of the additional signage that has been put in place following the feedback received from residents. 

If you have any further queries at this time, please feel free to send me a message by commenting on this post or emailing nwl.customer@esh.uk.com

I hope you all have a lovely week!

Thank you 

Becky 

 

Please Login in order to comment on this update.

Update by Rachel Rutter

Good afternoon,

This week the crew have been working on the following:

North Field & Haggs Lane

  • Archaeological works are ongoing for the installation of the rising main pipework.
  • The directional drilling and installation of the rising main completed on 10 May 2023.
  • Sand, geotextile and topsoil reinstatements are ongoing.

Haggs Lane

  • Haggs Lane Bridge works are ongoing for excavation/installation and backfill of the rising main.
  • The reconnection of the diverted water main is to be carried out week commencing 22 May 2023.

Greenford Lane

  • Once Haggs Lane Bridge works are completed the team will be returning to complete the installation of the Rising Main in this section.

Central Fields

  • The pipework installation and testing has been completed.
  • Reinstatement of the central fields and the installation of the field drains ae currently ongoing.

Birtley STW – Filter Beds

  • Excavation, installation and backfill of the Rising Main is ongoing within this section.
     

Please contact us direct if you have any questions at nwl.customer@esh.uk.com or 0191 3774500.

Thank you

Rachel 

Please Login in order to comment on this update.

Update by Rachel Rutter

Good morning,

I hope everyone is enjoying those long weekends!

The team are currently working on the below:

North Field & Haggs Lane

  • Archaeological works are in preparation for directional drilling, which is to be carried out on 2 May 2023
  • Haggs Lane Bridge works are ongoing for excavation, installation and backfill of the Rising Main.
  • Northumbrian Water have completed the excavation and temporary water main diversion; permanent water main diversion/connections will be done immediately after the rising main has been installed.

Greenford Lane

  • Once Haggs Lane Bridge works are completed the team will be returning to complete the installation of the Rising Main in this section.

Central Fields

  • Excavation, installation and backfill of the Rising Main Pipework is completed and testing of the pipework was carried out 28 April 2023.
  • The reinstatement of the central fields and installation of the field drains will commence 2 May 2023.

Birtley STW – Filter Beds

  • Excavation, installation and backfill of the Rising Main is ongoing within this section.
     

Please contact us direct if you have any questions at nwl.customer@esh.uk.com or 0191 3774500.

Thank you

Rachel 

Please Login in order to comment on this update.

Update by Rachel Rutter

Good morning, 

I hope everyone had a lovely weekend and made the most of the sun.

The team are currently working on the below:

North Field & Haggs Lane

  • Archaeological works are in preparation for directional drilling, which is to be carried out on 02 May 2023
  • The installation of the rising main and wash out chamber is ongoing.
  • Haggs Lane Bridge works recommenced from 11 April 2023 with the road closure in place for approximately 6 weeks.
  • The excavation and water main diversion commenced on 17 April 2023 for approximately 3 days.

Greenford Lane

  • Tarmac reinstatement was completed on the 04 April 2023 and all traffic management removed, while Haggs Lane Bridge closure is in place.

Central Fields/ Birtley STW – Filter Beds

  • The excavation, installation and backfill of the Rising Main pipework is ongoing within the central fields and will begin in the filter beds on 17 April 2023.

Birtley STW – Reed Beds

  • Installation of the Rising Main and excavation through the south reed beds are now complete.

Please contact us direct if you have any questions at nwl.customer@esh.uk.com or 0191 3774500.

Thank you

Rachel 

Please Login in order to comment on this update.

Update by Rachel Rutter

Good morning all, 

This week the crew have been working on the below:

North Field & Haggs Lane

  • ARS – Archaeological works and remobilise compound – Recommencing 03/04/2023 in the North Field
  • Haggs Lane Bridge works will recommence from 11/04/2023 with the road closed for approximately 6 weeks.

Greenford Lane

  • Construction of Chamber 5 High Point air valve at this location is completed.
  • Continuation with excavation, pipework installation and concrete back fill and tarmac reinstatement is ongoing up until 04/04/2023 – Traffic management will be removed to allow for Haggs Lane bridge closure before returning in approximately 6 weeks.

Central Fields

  • Works recommenced 20/03/2023 for the excavation, installation and backfill of the Rising Main Pipework.

Birtley STW

  • Excavation & Rising main installation through the South Reed Beds location is ongoing.

Moor Mill Lane/Greenford Lane – Staggered Junction

  • Survey works will take place outside of Birtley STW 03.04.2023 Traffic management will be in place with 2 way lights in operation for this day.
  • Pipe testing works will take place 04.04.2023 lane closure & 4-way lights will be required at the staggered junction for 1-2 days.
     

Please contact us direct if you have any questions at nwl.customer@esh.uk.com or 0191 3774500.

Thank you

Rachel 

 

Please Login in order to comment on this update.

Work in your Community

Work in a business that supports your community

At Northumbrian Water, we work to make a difference in your community.

Have you considered a career that can help you do the same?

As well as the teams you see working in your streets, we have people doing a wide range of jobs that support that work to deliver the best possible water and sewerage services across the North East.

You can find out more about careers with Northumbrian Water and check out the latest vacancies by following the link below.

www.nwl.co.uk/careers